STATE, COUNTY, CITY, SCHOOL WORK
MCGREGOR ACT LIEN
This schedule makes the following assumptions:
(1) That a subcontractor or supplier is filing the lien.
(2) That the subcontractor or supplier has a written contract with the General
Contractor.
ALL DATES ARE
MAXIMUMS - ALL FORMS CAN BE FILED EARLIER
ALL FORMS SENT BY CERTIFIED MAIL - RETURN RECEIPT REQUESTED
| Month that work was performed or materials were delivered | Notice
of claim and sworn statement to GC and Surety FORM 4-1 |
Date that contract was completed | No
later than 90 days following completion of contract send GC and Surety written notice of
unpaid Retainage FORM 4-3 |
Within 60 days following notice of unpaid claim, suit may be filed |
| JANUARY | APRIL 15 | JANUARY | APRIL | JUNE |
| FEBRUARY | MAY 15 | FEBRUARY | MAY | JULY |
| MARCH | JUNE 15 | MARCH | JUNE | AUGUST |
| APRIL | JULY 15 | APRIL | JULY | SEPTEMBER |
| MAY | AUGUST 15 | MAY | AUGUST | OCTOBER |
| JUNE | SEPTEMBER 15 | JUNE | SEPTEMBER | NOVEMBER |
| JULY | OCTOBER 15 | JULY | OCTOBER | DECEMBER |
| AUGUST | NOVEMBER 15 | AUGUST | NOVEMBER | JANUARY |
| SEPTEMBER | DECEMBER 15 | SEPTEMBER | DECEMBER | FEBRUARY |
| OCTOBER | JANUARY 15 | OCTOBER | JANUARY | MARCH |
| NOVEMBER | FEBRUARY 15 | NOVEMBER | FEBRUARY | APRIL |
| DECEMBER | MARCH 15 | DECEMBER | MARCH | MAY |