PRIVATE WORK
(NO GOVERNMENT INVOLVED)
LATEST DATES FOR MAILING NOTICES AND FILING AFFIDAVITS
[PROJECTS OTHER THAN RESIDENTIAL]
SOLD TO |
SOLD TO ORIGINAL CONTRACTOR: |
SOLD TO SUBCONTRACTOR: |
|||||
FIRST TIER CLAIMANT |
SECOND TIER CLAIMANT |
THIRD TIER CLAIMANT |
|||||
Month Work Furnished |
File Lien Affidavit Forms 1-A & 1-B |
(1) Special Notices See Below |
* Notice of Claim Form 2-A |
File Lien Affidavit Forms 1-A & 1-B |
Notice
to Original Contractor Form 3 Also |
* Notice of Claim Form 2-A |
File Lien Affidavit Forms 1-A & 1-B |
January |
May 15 |
March 15 |
April 15 |
May 15 |
March 15 |
April 15 |
May 15 |
February |
June 15 |
April 15 |
May 15 |
June 15 |
April 15 |
May 15 |
June 15 |
March |
July 15 |
May 15 |
June 15 |
July 15 |
May 15 |
June 15 |
July 15 |
April |
August 15 |
June 15 |
July 15 |
August 15 |
June 15 |
July 15 |
August 15 |
May |
September 15 |
July 15 |
August 15 |
September 15 |
July 15 |
August 15 |
September 15 |
June |
October 15 |
August 15 |
September 15 |
October 15 |
August 15 |
September 15 |
October 15 |
July |
November 15 |
September 15 |
October 15 |
November 15 |
September 15 |
October 15 |
November 15 |
August |
December 15 |
October 15 |
November 15 |
December 15 |
October 15 |
November 15 |
December 15 |
September |
January 15 |
November 15 |
December 15 |
January 15 |
November 15 |
December 15 |
January 15 |
October |
February 15 |
December 15 |
January 15 |
February 15 |
December 15 |
January 15 |
February 15 |
November |
March 15 |
January 15 |
February 15 |
March 15 |
January 15 |
February 15 |
March 15 |
December |
April 15 |
February 15 |
March 15 |
April 15 |
February 15 |
March 15 |
April 15 |
* Notice must be sent as to each month in which unpaid work is furnished: however, deadline for filing lien affidavits runs from last month in which work was furnished by claimant.