LATEST DATES FOR MAILING NOTICES AND FILING AFFIDAVITS
[PROJECTS OTHER THAN RESIDENTIAL]

 

SOLD TO
OWNER:

SOLD TO ORIGINAL CONTRACTOR:

SOLD TO SUBCONTRACTOR:

 

FIRST TIER CLAIMANT

SECOND TIER CLAIMANT

THIRD TIER CLAIMANT

Month Work Furnished

File Lien Affidavit Forms 1-A & 1-B

(1) Special Notices – See Below

* Notice of Claim Form 2-A

File Lien Affidavit Forms 1-A & 1-B

Notice to Original Contractor Form 3 Also
(1) Special Notices – See Below

* Notice of Claim Form 2-A

File Lien Affidavit Forms 1-A & 1-B

January

May 15

March 15

April 15

May 15

March 15

April 15

May 15

February

June 15

April 15

May 15

June 15

April 15

May 15

June 15

March

July 15

May 15

June 15

July 15

May 15

June 15

July 15

April

August 15

June 15

July 15

August 15

June 15

July 15

August 15

May

September 15

July 15

August 15

September 15

July 15

August 15

September 15

June

October 15

August 15

September 15

October 15

August 15

September 15

October 15

July

November 15

September 15

October 15

November 15

September 15

October 15

November 15

August

December 15

October 15

November 15

December 15

October 15

November 15

December 15

September

January 15

November 15

December 15

January 15

November 15

December 15

January 15

October

February 15

December 15

January 15

February 15

December 15

January 15

February 15

November

March 15

January 15

February 15

March 15

January 15

February 15

March 15

December

April 15

February 15

March 15

April 15

February 15

March 15

April 15

(1) Special Notices – Notice of Contractual Retainage – Form 4 and Notice for Specially Fabricated Materials – Form 5