FEDERAL WORK
MILLER ACT LIEN

This schedule makes the following assumptions:

  1. That a subcontractor or supplier is filing the lien.
  2. That the subcontractor or supplier has a contract with the General Contractor.
  3. That the amount to be recovered exceeds $100,000

Day in which work was
performed or materials delivered

Day at least 90 days after work was performed or materials were delivered but no later than 1 year after work performed or material delivered

FILE SUIT

JANUARY APRIL
FEBRUARY MAY
MARCH JUNE
APRIL JULY
MAY AUGUST
JUNE SEPTEMBER
JULY OCTOBER
AUGUST NOVEMBER
SEPTEMBER DECEMBER
OCTOBER JANUARY
NOVEMBER FEBRUARY
DECEMBER MARCH